Announcing your company won a national award for cutting-edge technology during your second week as their Marketing Manager is grand fun. It's even better when you crafted the submission for the award as a consultant for the firm. See all the 2020 Tibbetts Award Winners and Endurica's spotlight.
1/2
The City of Toledo is working through a 10-year, $500-million Ohio EPA-approved Plan of Capital Improvements at their Collins Park Water Treatment Plant. The largest and most difficult project in the plan, the Basin 7 & Basin 8 project, was awarded to Mosser Construction and is the most significant expansion of the Plant since 1956. Each basin provides 20 million gallons of drinking water per day through flocculation, sedimentation and recarbonation basins fitted with dual media filters, massive piping runs, masonry structures, and chemical feed facilities. Although built as one integrated project, the basins were sold and administered as two separate contracts, drawings and specifications. Project challenges included relocating multiple plant utility lines which bisected the site; a virtually inaccessible site hampered by road construction projects in one direction and a major train switching station on the other; extremely wet early spring site conditions requiring all excavated dirt to be moved off-site and later returned; a six-month soil consolidation period leading Mosser to secure an engineering firm to design a deep-foundation solution to mitigate schedule compression; an owner-directed change to the structural steel corrosion protection system causing distortion in the beam members, requiring flange extensions for masonry support and major masonry alignment challenges to match existing masonry coursings amid window openings and headers; a subsequent and adjacent project start which eliminated a significant section of Mosser’s laydown and staging area; and more. Mosser’s innovative naming/identification scheme and computer model tracked every pour in the 19,918 cubic yards of concrete needed for the basins, slab walls and decks in Basins 7 and 8. The project included $10,000 per day liquidated damage requirements but Mosser “finished strong” by beating both the EPA-mandated deadline – and Ohio’s state-wide COVID19 shutdown – by more than two weeks.
Thank you a million times over! This award is yours too!!! It's a bitter-sweet thing...happy we won, yet sad it was our last Build Ohio collaboration with you. Unless you change your mind...
Karen Boedeker
Marketing Coordinator/Proposal Manager
Mosser Construction
The Museum of Science at The Toledo Zoo was a Works Progress Administration project, built in 1933 with local materials recycled into an indoor theater and exhibit showplace. A treasure of hand-carved workmanship in both stone and fitted timbers, the Museum’s load-bearing masonry walls measure up to 18-inches thick and support a Spanish tile roof. The Museum hosted a wide variety of exhibits through the 1980s, then transitioned into offices and research space. In 2015, the Zoo created a master plan which included bringing the structure into code-compliance and back to life as a vibrant, exciting architectural treasure.
Transforming the WPA-era museum into an entirely new visitor experience created major challenges for A.A. Boos & Sons, general and interior trades contractors for the project. To carry the loads of today’s visitors, displays, water features and exhibits, the firm had extensive shoring engineered to brace the structure, added 1,245 pieces of structural steel, poured 650 cubic yards of structural concrete and 85 cubic yards of exhibit Gunite. Since original columns do not align from one floor to the next, this shoring was also critical in the creation of 15 significant openings made in load-bearing brick walls as well as the re-alignment of the first floor. Over eighty-percent of the basement was removed and A.A. Boos excavated 1,200 cubic yards of dirt through standard (3′ x 7′) doors while removing and lowering the theater’s sloped floor to meet code and accessibility requirements. Over 300 field work orders were completed with well over one hundred additional tasks done the week the Museum opened to the public. A.A. Boos self-performed 45,000 man-hours of work with no lost-time injuries while protecting the architectural integrity of the Museum, finishing without a single crack in the brick structure, ornate stone detailing or treasured woodwork.
Thank you for the hard work and effort you put into our submission. It was evident by the way everyone perceived our project at the banquet that the entry was professional and met all the criteria. You truly have a gift when it comes to delivering a project's history and uniqueness.
Stan Delventhal
President
A.A. Boos & Sons, Inc.
Mosser Construction
Fremont, Ohio
Excellence in Renovation over $10 Million
for
University Hall Renovation
Bowling Green State University
Mosser Construction
Fremont, Ohio
Excellence in New Construction
Under $10 Million
for the
Ronald McDonald House
of Northwest Ohio.
Mosser Construction
Fremont, Ohio
Excellence in Specialty Construction
for
The University of Toledo's Interprofessional Immersive Simulation Center.
A.A. Boos & Sons, Inc.
Oregon, Ohio
Excellence in Specialty Construction
for
Cedar Point's
GateKeeper Foundations
Turner Construction Company
Cincinnati, Ohio
Excellence in New Construction
Over $20 Million
for
The Great American Tower
at Queen City Square
Mosser Construction
Fremont, Ohio
Excellence in Construction Renovation
for
The University of Toledo
Savage Arena Renovation
Women in Communications
Toledo Chapter
Crystals Award Program
Move Ohio Award Competition
Ohio Contractors Association
Mosser Construction
for
Wet Weather Facilities
Bay View Wastewater Treatment Plant
Toledo, Ohio
Build Ohio
Bostleman Corporation
Excellence in Construction
Under $10 million
for
B'nai Israel Temple
Sylvania, Ohio
Build Ohio Award Competition
Mosser Construction
Excellence in Construction under $10- million
for
American Maritime Officer's
McKay Training Center
Toledo, Ohio
Build Ohio Award Competition
Bostleman Corporation
Excellence in Construction Management
for
Trinity Episcopal Church
Toledo, Ohio.
Collaborated on winning entry for
Mosser Construction
AGC of America
Marvin M. Black
Excellence In Partnering Award
U.S. Army Reserve Center